Jun 18, 2025

Hays High proceeds on schedule, budget but without murals

Posted Jun 18, 2025 10:01 AM
The turf has been laid for the new Hays High School football field. The school is scheduled to open in August, in time for the start of the 2025-26 school year. Courtesy photo
The turf has been laid for the new Hays High School football field. The school is scheduled to open in August, in time for the start of the 2025-26 school year. Courtesy photo

By CRISTINA JANNEY
Hays Post

The construction of the new Hays High School is on budget and on schedule to open in August at the start of the school year.

Nabholz Construction provided an update on the construction project and presented information about a proposed change order for the high school.

Turf has been laid on the athletic fields. Flooring is almost complete in the two gyms, and work on the bleachers is ongoing.

Workers are completing the punch list on areas A and B of the high school. This includes the science labs.

Newly turfed Hays High soccer field. Courtesy photo
Newly turfed Hays High soccer field. Courtesy photo
Hays High football field. The home bleachers and atheltic wing can be seen on the right. Courtesy photo
Hays High football field. The home bleachers and atheltic wing can be seen on the right. Courtesy photo

The west wing, which includes parts A and B, the center atrium (area C) and the east wing (areas D and E), is set to be substantially complete by July 7.

The rest of the project is scheduled to be substantially complete by Aug. 13.

High school change order

Complete bond projects budget. The school board did not approved $38,000 for murals at Hays High School in the latest change order for the project. More than $300,000 remains in the Hays High School contingency fund.
Complete bond projects budget. The school board did not approved $38,000 for murals at Hays High School in the latest change order for the project. More than $300,000 remains in the Hays High School contingency fund.

Dylan Weddle, Nabholz project manager, presented the board with $111,062 in change orders for the Hays High project at the school board meeting Monday night.

The change orders are still well within the $1 million contingency fund established for the project. With the latest change orders that have been approved, more than $300,000 remains in the high school project's contingency fund, with the project nearing completion.

The change order included modifications to the track and field layout. Superintendent Ron Wilson said after a meeting with coaches, it was decided there wasn't enough room between the pole vault and high jump areas, so the designers moved the pole vault area.

There were similar concerns about the two discus rings being too close together. The change order also included some changes to the sidewalks in the softball and baseball areas.

Main gym. Courtesy photo
Main gym. Courtesy photo
The school board voted  Monday to not pay for a change order for murals for the new Hays High School. This mural in the auxillary gym was already completed, and Nabholz Construction will have to eat the cost of the painting. Courtesy photo
The school board voted  Monday to not pay for a change order for murals for the new Hays High School. This mural in the auxillary gym was already completed, and Nabholz Construction will have to eat the cost of the painting. Courtesy photo

The board did not approve the $38,000 change order for murals inside the high school.

Weddle said one of these murals in the auxiliary gym is complete. He said Nabholz moved forward with the painting to keep the project on schedule.

He said the murals were not included in the original budget because the designers and the district were undecided about their placement until the project was under construction.

Because the school board did not approve that change order, Nabholz will be responsible for the work that has already been done.

Board member Derek Yarmer said he saw the murals as an unneeded expense.

The entrances for the new high school have been completed. Courtesy photos
The entrances for the new high school have been completed. Courtesy photos

Yarmer said he thought the district should dedicate the $38,000 to other buildings in the district.

Board President Curt Vainar and Vice President Jayme Goetz said the district could revisit the murals once all of the other bond projects are complete.

Board member Ruth Ruder said, "We are going to have this big, beautiful high school and we're not going to see these murals for a year or two or five years."

Board member Ken Brooks noted the murals will cost more if they are delayed.

He added, "We're cheating them out of money."

He said that is not the way to treat a company that provides good work for the district.

Goetz said, "That's the risk that's involved."

Academic areas in the new high school are nearing completion. On the left is a special education classroom. On the right is a science classroom. Courtesy photos
Academic areas in the new high school are nearing completion. On the left is a special education classroom. On the right is a science classroom. Courtesy photos

Ruder noted Roosevelt had murals and logos in its new addition. She emphasized that branding is important.

Yarmer argued spending the $38,000 on the murals was going to prevent bathrooms from being repaired in other buildings.

Brooks said no, it was not. The funds for the murals were well within the contingency fund for the high school.

"We can have both," Brooks said.

Yarmer said, "We can't the way we are spending money."

The motion to approve the change orders without the murals passed on a vote of 4-3, with Brooks, Ruder and Meagan Zampieri-Lillpopp voting against.

Brooks asked again after the vote what the district was going to do to compensate Nabholz for the mural that had already been completed.

Yarmer said, "It's free."

Weddle said Nabholz would not charge the district for the completed mural.