Main St. brick repair ahead of schedule; closings changed

Posted May 12, 2020 5:29 PM

CITY OF HAYS

On Monday, May 11, Morgan Brothers Construction, a contractor for the city of Hays, began the repair of settled joints in the brick pavement on Main Street between 6th and 13th Streets.

Work began at 6th Street and is progress northward.

Progress is ahead of schedule, and the project is expected to be completed by the end of the day on Thursday, May 14, rather than Friday as originally anticipated.

The 800 block of Main will be closed this afternoon (Tuesday) and Wednesday morning; the 1000 block of Main will be closed Wednesday afternoon; the 1100 block will be closed Thursday morning; and the 1200 block will be closed Thursday afternoon.

Main Street will be closed to traffic one block at a time as work progresses.

Sidewalks and side streets will remain open.

For questions contact the Office of Project Management at (785) 628-7350 or Morgan Brothers Construction at (785) 432-3104.