Roosevelt Elementary School staff members will move into the school's new addition on Nov. 25 and 26.
Students are set to move into the new space on Dec. 2, the Monday after Thanksgiving.
The district has set an open house and ribbon cutting for 5:30 p.m. Dec. 2 at the school.
This week, the contractors plan to finish their punch list and complete the final cleaning.
At the new high school site, work is continuing to enclose areas of the building so construction can continue during the winter months. Structural steel is going up in area F. Metal wall panels have been installed in area A.
Turf also has been installed at the high school softball fields.