O'Loughlin, Felten renovations progress; O'Loughlin to release early for summer

Posted May 15, 2026 9:45 AM
North O'Loughlin Elementary School addition that will house classrooms and function as a storm shelter. A walk through of the two new additions is scheduled for the week of May 25. Courtesy photo
North O'Loughlin Elementary School addition that will house classrooms and function as a storm shelter. A walk through of the two new additions is scheduled for the week of May 25. Courtesy photo

By CRISTINA JANNEY
Hays Post

On Tuesday night, Hays USD 489 received a report on the progress of the bond-funded renovations at O'Loughlin Elementary School and Felten Elementary School (formerly Hays Middle School).

Both projects are scheduled to be completed in August.

The south O'Loughlin addition includes a new entrance, cafeteria and art room. Courtesy photo
The south O'Loughlin addition includes a new entrance, cafeteria and art room. Courtesy photo

O'Loughlin

Two additions are being added to O'Loughlin.

The north addition will include classrooms and a storm shelter. 

The south addition includes a new entrance, cafeteria and art room.

Last week at O'Loughlin, ceiling tiles were installed, a final coat of paint was done on the north addition, countertops and flooring were installed, and lighting was turned on.

New lighting and ceiling tiles being installed at O'Loughlin. Courtesy photo
New lighting and ceiling tiles being installed at O'Loughlin. Courtesy photo

This week, electrical work is being done along with more painting, doors are being installed, concrete for sidewalks are being poured, more flooring work will be done and plumbing work.

The contractors are estimating they will be able to have a walk through of the new additions by the week of May 25.

A new drive is being added south of O'Loughlin to allow for better vehicle stacking during student pick up and drop off. Now vehicles block traffic on Hall Street during these times. Courtesy photo
A new drive is being added south of O'Loughlin to allow for better vehicle stacking during student pick up and drop off. Now vehicles block traffic on Hall Street during these times. Courtesy photo

Summer work will begin at O'Loughlin on Wednesday. O'Loughlin is only releasing for the summer today to allow workers to start on renovations on the older section of the school.

This will include $1 million for sewer replacement. 

Concrete was laid to fill in areas where plumbing was installed at Felten Elementary. Bathrooms are being added for the lower grades at the new elementary school. Courtesy photo
Concrete was laid to fill in areas where plumbing was installed at Felten Elementary. Bathrooms are being added for the lower grades at the new elementary school. Courtesy photo

Felten

Work is ongoing at Felten Elementary School.

Last week demolition continued at the school, some areas were framed, walls were painted in areas that were not affected by plumbing upgrades, and concrete was laid in areas where plumbing work had been done.

Next week, site grading will be done, drywall and ceiling grids will be hung, framing and painting will be done, and more demolition will be completed.

Cabinets being demolished at Felten Elementary School. Courtesy photo
Cabinets being demolished at Felten Elementary School. Courtesy photo
Framing being complete at Felten Elementary School. Courtesy photo
Framing being complete at Felten Elementary School. Courtesy photo

Wilson Elementary School will be closed at the end of the school year as an elementary school.

Wilson students will be moved to Felten.

The district hopes eventually to remodel Wilson for use as an administrative center, and close Rockwell and possibly sell the property.